TABLE
OF CONTENTS
CHAPTER ONE
INTRODUCTION
1.1 BACKGROUND TO THE STUDY
1.2 STATEMENT OF THE PROBLEM
1.3 AIMS AND OBJECTIVES
1.4 HYPOTHESIS.
1.5 SIGNIFICANT OF STUDY.
1.6 SCOPE AND LIMITATION.
CHAPTER TWO
2.0 INTRODUCTION
2.1 THE CONSTRUCTION SITE.
2.2 CONSTRUCTION MATERIALS.
2.3 NATURE AND CLASSIFICATION OF
MATERIAL.
2.3.1 BULK
2.3.2 BAGGED
2.3.3
PALLETED
2.3.4
PACKAGES
2.3.5
LOOSE
2.4 THE COST OF MATERIALS
2.4.1
DELIVERY
TO SITE.
2.4.2 UPLOADING
2.4.3
SHRINKAGE:
2.4.4
LAPS
2.4.5
BULKING
2.4.6
COMPACTION:
2.4.7
WASTE
2.5 PRETENDER ALLOWANCE FOR WASTE
2.6 MATERIALS WASTAGE
2.7 TYPES AND SOURCES OF WASTE
2.7.1 DIRECT WASTE
2.7.2 INDIRECT WASTE
2.8 EFFECT OF MATERIALS WASTAGE ON
CONSTRUCTION OUTPUT.
2.9
MATERIAL MANAGEMENT
FUNCTIONS
2.9.1 SCHEDULING /
PLANNING NETWORK
2.9.1 PRE – TENDER PLANNING
2.9.2 PROCUREMENT
NETWORK.
2.9.3 PROCUREMENT
PROCEDURE
2.9.4 PHYSICAL /
CONTROL AND STORAGE.
2.9.5 USAGE
2.10 METHODS OF
MATERIALS WASTE REDUCTION
2.11 SITE
ACCOUNTING SYSTEM.
2.12 CONTROL
FORMS
2.12.1 THE
MATERIAL BUDGET
2.12.2
REQUISITION ORDER
2.12.3 DELIVERY NOTE
2.12.4 MATERIALS
RECORD BOOK
2.12.5 MATERIAL
TRANSFER NOTE
2.12.6 MATERIALS
ALLOCATION
2.12.6.1 “IN AND
OUT’’ BIN CARD
2.12.6.2
INVENTORY BIN CARD
2.13 MATERIAL
BOOK
2.14
COMPUTERIZED RECORDS
2.15 MATERIAL
RECONCILIATION
2.16 MATERIALS
HANDLING AND CONTROL STORE KEEPING
2.17.2 WORK IN
PROGRESS INVENTORY
2.17.3 FINISHED
GOODS INVENTORY
2.18 INVENTORY
CONTROL TERMINOLOGIES
2.18.1 LEAD OF PROCUREMENT TIME
2.18.2 ECONOMIC ORDER QUANTITY
(EBQ) OR ECONOMIC BATCH QUANTITY (EBQ)
2.18.3 BUFFER
STOCK OR MINIMUM STOCK OR SAFETY STOCK
2.19 INVENTORY
MANAGEMENT TECHNIQUES
2.19.2 THE RE-ORDER
POINT (ROP)
2.2.1 PRICING
STORES ISSUES
2.21.1 FIFO
(FIRST IN, FIRST OUT)
2.12.2 LIFO
(LAST IN, FIRST OUT)
2.21.3 AVERAGE
PRICE METHOD
2.21.4 STANDARD
PRICE
2.21.5
REPLACEMENT PRICE
2.21.6 BASE
STOCK METHOD
2.22 MATERIAL
HANDLING AND CONTROL STORE KEEPING
CHAPTER THREE
3.0
DATA PRESENTATION AND ANALYSIS
3.1 DATA ANALYSIS AND HYPOTHESIS TESTING
3.2 DATA
ANALYSIS AND HYPOTHESIS TESTING 1
3.3 DATA
ANALYSIS AND HYPOTHESIS TESTING III
3.4 DISCUSSION OF FINDINGS
CHAPTER FOUR
CONCLUSION AND
RECOMMENDATIONS
4.1 CONCLUSION
REFERENCE
APPENDIX
APPENDIX II
QUESTIONNAIRE II
CHAPTER ONE
INTRODUCTION
1.1 BACKGROUND TO THE STUDY
Project
delivery in the Nigeria construction industry is largely characterized by
abandonment and delay at varied stages of completion. This pathetic situation
is borne out of the construction of management in the industry on labour
productivity thereby relegating to the background the importance of materials
employed in job-execution.
The
cost of materials constitutes 50-60% of the total cost of construction. The
costs and value have a direct and blank- range effects on the overall cost and
value of a building.
The word ‘’construction’’ is an all
embracing term which covers works involved in the erection of buildings for
various uses such as; private and public residential buildings for various uses
such as; private and public residential buildings, commercial, industry,
healthcare and recreation. It also covers all engineering works such as roads,
bridges, dams, drainage’s and Sir fields e.t.c. the widespread of activities
indicated a very high financial resource involvement. In 2005 alone, Nigeria
spent ₦8.0
billion on the construction industry on non- residential buildings as reported
by Ademoroti (2009). This figure accounted for 53.3% of the gross capital
investment at current purchaser’s value at that time without doubt the
construction industry is regarded as a highly capital intensive industry which
requires a lot input which if not properly managed will result in great loss.
The
very long process of construction procedure makes it more susceptible to losses
and wastages. Starting from the process of construction, wastage abound.
The
construction process which can be equated to the production process of the
manufacturing industry takes place on the construction site, and is regarded as
the most vital in the construction industry. This assertion is corroborated by Newcomb
et al 2009 ‘’ At the heart of a construction organization is the building site.
Therefore the construction production is the dominant process performed’’.
Unlike other industries where factory processes are bored on clearly defined
past practices and are often largely determined by fixed plant and machinery Seeley
(2010).
Site management in the Nigeria
construction industry has tended to be focused mainly on labour organization
and productivity to the negligence of materials. However of the five resources
that go into production process identified by ward (2011) are:
i.
Men (Labour)
ii.
Materials
iii.
Money (Capital)
iv.
Machines (Equipment)
It
is generally recognized that materials constitute a high percentage. This
universal truth has been extracted by Wahab (2005) from 2009 United Nation
Industrial development Organization (UNIDO) sponsored work report which
revealed that building materials and components contribute between 50 and 60
percent of the total value of construction output. Based on this high figure,
materials management should not be toyed with. On the other hand, an effective
materials management will lead to a substantial cost savings and increased
profitability to the client and the contractor respectively. A small percentage
cut in materials wastage could bring about a sizeable increase in profit.
Waste
come about in different forms on construction sites. example are waste from
cut-off, bad storage, transportation e.t.c. Alabi (2011) asserted that if
resources are used beyond a particular level in relation to the real values
they are wasted. A much more detailed description of wastages by Skoles (2012)
states that ‘’the general recognition that not all materials delivered to the
construction sites are used for the purpose for which they are ordered and that
builders frequently use more materials than those for which they receive
payment. These materials are neither lost or are used in construction process
in ways that are not recognized by estimators. These differences have never
been clearly defined and are collectively referred to as waste’’.
Materials
wastage on construction sites are often taken for granted. It should how ever
be appreciated that whatever the degree of waste, it has a cost implication. A
very serious case of wastage could result in colossal loss of profit to the
contractor. As such construction firms wanting to survive in this very hard
economic recession which has led to stiffer competition in rates quotation and
tendering must place more emphasis on materials wastage control, as it will
help to raise profitability.
In
Nigeria, the very big projects are handled by the few foreign firm most
especially heavy civil works, tall buildings e.t.c. while small and medium
scale jobs such as school projects, housing estates and private residential
developments, on all of these projects evidences of material wastage are seen
in the form of heaps of unwanted materials, old and new, littering the sites.
The
study is the focused on control of building materials on construction site and
the possible causes of materials wastage on construction sites, and also the
ways of controlling them with a view towards minimizing losses and at the same
time improving the contractor’s profit margin.
1.2 STATEMENT OF THE PROBLEM
Wastage
arises through such cases as damage, theft misuse, using incorrect material,
negligence, in cutting and preparing, and over specification. Whatever the
circumstances, the implication is a monetary loss arising from increased cost
and quantity of material used as against the measured work, when losses or
wastage become very severe, the result may be a complete loss of profit to the
contractor.
For
contractors to improve upon their profit margin and also reduce losses on
scarce material resources. There is need for the established of effective
control mechanism over materials all through material phases on construction
projects. Not only does materials wastage reduce the profit level of the
contractor, its adverse effect on construction works has also been linked to
project delay and abandonment.
In
the light of these shortcomings, improving material control on the sites.
1.3 AIMS AND OBJECTIVES
This
project is aimed to examine the control of building materials on construction
site to reduce materials wastage and correspondingly increase the contractor’s
profit margin.
The
objectives are;
i.
To determine and causes of
materials wastage on construction site.
ii.
To determine whether construction
firms adhered to the use of inventory control forms.
iii.
To determine an effective method
for materials control construction site.
iv.
To proffer solution to the
materials on construction site.
1.4 HYPOTHESIS.
HYPOTHESIS I:-
To
test whether or not there is a statistically significant relationship between
the method of materials management policies / practice and the level of wastage
experienced on construction sites.
HYPOTHESIS
II:-
To
test whether there is a statistically significant relationship between wastage
of materials on site and the mode of transport / delivery to construction site.
HYPOTHESIS III:-
To
test whether there is a statistically significant relationship between wastage
of materials that will occur on site during usage of materials and type of
construction activity.
1.5 SIGNIFICANCE OF STUDY
Primarily
project work titled ‘’Inventory Management – control of building materials on
construction sites’’ is aimed at determining the factors leading to and
contributing to wastages of materials and the inventory management practice on construction
sites. Thereafter suggesting the ways of reducing such losses of materials
resource.
Materials
constitute a large percentage of all resources that goes into the physical
development of buildings or other structures. These materials have cost
implications, they are scarce just as well as money is scarce and should
therefore be treated as well.
Construction
processes by its very nature allow for wastages to occur, it is often prone to
large scale waste if proper attention is not paid to materials both in handling
and in storage. Since wastage is a loss in monetary terms, a large scale loss
may result in complete loss of profit to contractor most especially in this
present days of competitive tendering resulting in low percentage charges on
profit and overheads.
Materials
control is not a particularly new term to the construction firms, but the
existence of the total concept of carrying out the control measures,
observations, have shown that the operative especially and some supervisors
exhibit a lot of indifference to the issue of wastage. Apart from the cost
reduction effect it has on the contractor’s profits. It also constitute a
menace to easy flow of work on site. There is greater risk of accident to operatives
and other personnel on site and also plants hired tend to stay longer on sites
due to delay, which may be experienced.
There
is a need to check all the negative tendencies occasioned by wastage of
materials on site. Whatever the source of the waste, a through control will
bring about a reduction in the wastage and an ultimate increase in profit
return.
Finally
to realize such profit return, there is a need for a solid materials management policy put in place to check or
guide against all sources of materials loss, and it is the responsibility of all private authorities to ensure that
resources are utilized to an optimum level.
1.6 SCOPE AND LIMITATION.
The
general scope of this research covered some problems associated with materials
wastage on construction sites and is restricted to minimizing wastage. It is
limited to inventory control and accounting control of building materials. The
materials referred to in the context of this paper is limited to those
materials classified as required medium to much protection.
Only
some common sources of wastage will be considered in the research work. And the
basic traditional economic order models are considered as an inventory control
model and no mathematical model will be applied. Material considered are the
general types like cement, concrete block, plumbing material e.t.c.
Login To Comment